LONDON: Subsidized renewable energy cuts peak power prices, but is also unreliable, and in most countries the cost of balancing its intermittency is borne by dispatchable (available on demand) fossil fuel and nuclear power.
Dispatchable power providers are pressing claims for subsidies to provide this backup, which would not only keep the lights on but also stop power prices spiking out of control every time they have to step in when wind or solar fails, as can be the case.
Without support for these balancing services some forms of dispatchable power will become uneconomic and unsustainable, because renewables generate power at zero marginal cost.
In the short run, the most affected technologies will be those with higher generating costs, including flexible gas-fired power plants which grid operators presently use as a standing reserve.
But in the long run, high capital cost coal and nuclear will also suffer because lower average peak power prices will make it more difficult for them to raise finance to build new plants, according to a new study by the OECD’s Nuclear Energy Agency.
At present, there is little evidence that European policymakers have fully thought through the problem, for example about whether they subsidize balancing services, and if so, gas, nuclear or coal.
Grid operators already need reserve capacity to respond to variations in demand and unexpected tripping of conventional power plants.
There are two types of reserve: an operating reserve that must be available within 10 minutes or so, and a replacement reserve which takes over within an hour.
For operating reserve there are various options, including flexible offline capacity which can fire up from cold very quickly (called a standing reserve), or a spinning reserve of online plants which are already running at part-load and can ramp up by applying more torque.
Open cycle gas turbines (OCGT) have the fastest start-up times.
These simple power plants were introduced decades ago to supply peak-load service: air is compressed and used to fire natural gas in a combustion chamber which drives a gas-turbine and electricity generator on a single shaft.
They have rather low electrical efficiency because they fail to recycle hot exhaust gases.
But their simplicity gives them a quick start-up time of 10 to 20 minutes, according to the NEA’s “Nuclear Energy and Renewables: System Effects in Low-Carbon Electricity Systems,” published recently.
Since the early 1990s, combined-cycle gas turbines (CCGT) have become the technology of choice for new gas-fired power.
They use gas-turbine exhausts to generate steam that drives an additional steam-turbine generator to produce more power.
They have electrical efficiencies of 60 percent or more.
From cold, they have a slower start-up than OCGTs, at 30-60 minutes, according to the NEA, but still faster than coal, at 1 to 10 hours, and nuclear, at two hours to two days. (see Figure 1)
Intermittent wind and solar power now accounts for a significant and rapidly rising share of electricity generation in some European countries, notably Denmark, at 28 percent last year, as well as Spain (18 percent) and Germany (11 percent), according to BP data.
Markets in these countries where penetration of renewable energy is high have been up-ended, driving down average peak wholesale prices and hitting the profitability of traditional power providers.
OCGT is the most vulnerable to a mainstreaming of renewable power, given it has the highest generation costs.
The NEA report estimated that OCGT profitability would drop by more than 80 percent when wind power reached a third of installed capacity, while the profits of even least-impacted nuclear power would fall by more than half.
But if countries start paying for balancing services, such calculations will be again turned on their head.
Some gas engine suppliers sense an opportunity, such as Finnish power plant engine maker Wartsila, which is marketing a gas plant which can shut down the combined cycle of a CCGT, to ramp up faster.
The NEA says it sees a new role for nuclear power, as the least carbon-emitting dispatchable option.
Nuclear is usually operated as baseload, meaning power plants are run for more than 5,000 hours annually.
That is partly for economic reasons, to capitalize on low running costs and pay back the high, upfront capital costs, as well as safety ones, connected with control of core temperature and constraints imposed by the life-cycle of the fuel rods.
More frequent cycling of the power plant could also speed up materials fatigue, says the NEA.
After taking those constraints into account, online nuclear power plants can be ramped up and down about as quickly as a coal plant, the NEA said, adding that French nuclear power was already used to vary output according to demand.
However, the NEA’s own estimate of nuclear power start-up and ramp-up times suggests it may struggle to compete with gas.
Governments are struggling to keep up with the demands of a more variable grid.
European Union policy for example focuses on the adequacy (amount) of member states’ reserve capacity, rather than their responsiveness.
“Currently, the ENTSOE (European Network of Transmission System Operators for Electricity) generation adequacy assessment does not focus on the flexibility of the system, and its ability to cope with large swings in the feed in of variable wind and solar generation,” said a European Commission paper consulting on generation adequacy, published earlier this month.
And where the need for flexibility is recognized, supply options have a job competing with alternatives, including demand-side responses (cutting supply at peak times to consenting users) and smart grid options.
Britain’s Department of Energy and Climate Change in August published a report, “Electricity System: Assessment of Future Challenges,” which focused on these rather than using more flexible power plants.
And Germany recently passed legislation where grid operators could agree to pay industrial consumers to interrupt their supply and so provide flexibility at peak times.
— The author is a Reuters market analyst. The views expressed are his own.

What's happening around Saudi Arabia

JEDDAH: For Moneera, a working Saudi woman, going from her home to the workplace took 10 times what it usually takes because of the rains that recently fell on Jeddah. The half hour it takes to reach her home, despite congestion on the road, was exte...
RIYADH: The flood situation in Buraidah remained grim on Saturday, two days after the rains stopped. The poor precautionary measures taken and the limited work done to avoid flooding of the main streets and neighborhoods paralyzed vehicular traffic a...
JEDDAH: Around 250,000 Umrah pilgrims have booked hotel rooms in Makkah and Madinah through the new “Sijjil” electronic system, Abdullah Qadi, deputy president of the National Committee for Haj and Umrah, has said.Reserving hotel accommodation throug...
JEDDAH: The director of the Health Department in Jazan, Ahmed bin Mohammed Al-Sahli, has said that the Health Ministry will pay SR20 million to workers at hospitals in the southern borders, pointing out that these incentives had been promised by the...
JEDDAH: Abdul Rahman Al-Yahya, director general of the Passport Department, announced that plans to set up a one-stop border crossing post at King Fahd Causeway have been postponed.The plans were postponed because negotiations and the testing were de...
RIYADH: Top academics have called for a concerted drive against domestic violence in cases involving child abuse.Describing it as a global phenomenon, they called for raising public awareness and other means to protect children from abuse.The experts...
MAKKAH: An Umrah pilgrim was killed and 17 others, one of them critically, were injured when their bus hit a truck on the Madinah-Makkah highway early Friday morning. The bus, carrying 40 pilgrims from Eastern Province, rammed the truck from behind,...
JEDDAH: A seminar on energy efficiency in the automobile sector was held as part of the 60th anniversary of the establishment of diplomatic relations between Saudi Arabia and Japan, at Saudi Japanese Automobile High Institute (SJAHI) in Jeddah on Thu...
RIYADH: The real estate sector is upbeat about the recent Cabinet decision to impose a 2.5 percent tax annually on vacant land in urban areas, saying that the move will create investment opportunities and generate employment. Only a handful of big p...
RIYADH: Sir Syed Ahmed Khan truly inspires us showing the way for tolerance and unity in diversity by considering Hindus and Muslims as two eyes of India; and if one of them is hurt, the beauty of India is spoiled, Congress leader and actor Raj Babba...
JEDDAH: Recruitment visas in the private sector totaled 1.6 million in 2014, according to a Ministry of Labor report.At the same time, the recruitment of domestic workers involved 847,927 visas during the year, the report published by a local newspap...
DAMMAM: Aligarh Muslim University alumni of Alkhobar and Dammam celebrated the annual Sir Syed Day recently.Guest of honors and senior Aligarians shared the vision of Sir Syed Ahmad Khan on empowerment of Muslims through education.Cultural activities...
MAKKAH: A lawyer has been charged with holding a fake degree certificate and also getting a license for a clinic in Taif through fraudulent means. According to local media, the documentation of a doctoral dissertation in the Education Ministry reveal...
MOSCOW: Abdullatif Al-Othman, governor of Saudi Arabian General Investment Authority (SAGIA), has stressed the depth of Saudi-Russian cooperation in the fields of development and investment.In a joint press conference on Friday with Russian Energy Mi...
RIYADH: Another wave of bad weather is likely to affect the Kingdom Tuesday through Friday.The Presidency of Meteorology and Environment (PME) announced Friday that rains coupled with thunderstorms are expected to lash Hail, Qassim, Madinah, the Nort...

Events & Exhibitions

Stay Connected