Under the contract, Hyosung Power and Industrial Systems, a
leading electrical equipment and industrial machinery provider, will build six
220-kilovolt and two 66-kilovolt electrical transformer substations by the end
of 2013.
Hyosung added the affiliate will be responsible not only for
the construction but also for engineering and procurement for the Qatar
project.
In the previous Qatar deal, Hyosung Power and Industrial
Systems clinched a 130 billion won order to build three 132-KV and two 66-KV
substations in the Middle Eastern country, which are scheduled to be completed
next year, according to the company.