Saudi conjoined twins separated

Saudi conjoined twins separated
Dr. Abdullah Al-Rabeeah and his team of doctors separate the conjoined twins in the operation room. (SPA)
Updated 15 October 2016

Saudi conjoined twins separated

Saudi conjoined twins separated

RIYADH: Saudi conjoined twins were successfully separated in a five-hour surgery Thursday by a surgical and multidisciplinary team headed by Dr. Abdullah Al-Rabeeah. 
The separation took place at the King Abdullah Specialist Children’s Hospital at the King Abdul Aziz Medical City, Ministry of National Guard— Health Affairs in Riyadh based on a directive of Custodian of the Two Holy Mosques King Salman.
The conjoined twins, Eylan and Eleen who weighed 3.6 kg at birth, were delivered by a caesarean section at the King Abdul Aziz Medical City–Riyadh, when the mother was in the 34th week of her pregnancy.
According to a spokesman for the hospital, the surgery, which started at 7:20 a.m., ended successfully at noon Thursday, and the twins were placed on two separate cots in the pediatric intensive care unit of the hospital.
Al-Rabeeah said that the twins underwent clinical tests, which showed they were conjoined at the abdominal wall and the lower chest, and they shared the liver with abdominal wall defects.
The twin Eylan suffered from congenital defects, where she had disruption in the abdominal wall and the bladder, and a fistula between the small intestine and bladder. She also suffered from spinal cord, vertebral column and brain abnormalities.
Prior to the surgery, Al-Rabeeah confirmed that, in the light of these abnormalities, the risk rate of the operation for Eylan was up to 80 percent, which was the reason behind bringing the operation forward to save Eleen‘s life. Al-Rabeeah had expected the procedure to last for up to seven hours with the participation of the multidisciplinary team. The parents thanked Custodian of the Two Holy Mosques King Salman who magnanimously ordered the separation surgery.
Thursday’s separation was the 41st surgery to be performed on conjoined twins in the Kingdom since 1990, on cases from more than 18 countries.
Saudi Arabia has a team of top surgeons specializing in the separation of twins, with experience in treating more than 94 twins, of which 32 have been successful during the past two decades. The remaining cases were not fit for separation owing to health reasons.
Besides the Kingdom, the twins came from Sudan, Syria, Yemen, Egypt, Malaysia, the Philippines, Poland, Morocco and Iraq.
Al-Rabeah, who is the president of medical and surgical team in separating Siamese twins, was the former health minister and is currently the general supervisor of the King Salman Humanitarian Aid and Relief Center. He is a surgeon of repute and is known as the pioneer of separation surgeries in the Kingdom.
The separation of conjoined twins is carried out on directives issued by the king and the total expenses of the surgery and the related costs are borne by the Saudi government as a humanitarian gesture.


Overdue business rents waived by Saudi court

Overdue business rents waived by Saudi court
If a contract obliges one of the parties to carry out a task, which cannot be completed on time due to the pandemic, the court can temporarily suspend the implementation of the obligation. (SPA)
Updated 19 January 2021

Overdue business rents waived by Saudi court

Overdue business rents waived by Saudi court
  • The new regulations cover construction contracts, supply contracts, and the like, which have been affected by the pandemic

RIYADH: The General Assembly of the Saudi Supreme Court has ordered the waiving of overdue rents on businesses hit by the coronavirus disease (COVID-19) pandemic, and called for a review of such contracts between tenants and owners.

The steps have been taken in view of the circumstances caused by the pandemic, wherein an obligation or contract cannot be implemented without unusual losses.

The president of the Supreme Court, Khalid bin Abdullah bin Muhammad Al-Luhaidan, approved the decisions backed by 32 members of the assembly, Okaz newspaper reported.

Authorities have set conditions that have to be met before a case can be considered for review under the new regulations.

If a contract was concluded before the commencement of the preventive measures announced in the wake of the pandemic, then the impact was direct and unavoidable. If in such a case, an affected party was not compensated or did not reach a deal to mitigate the impact of the health crisis, then it qualifies for a review and the new regulations will then take effect, said legal sources.

The Supreme Court said a competent court will issue its verdict based on facts and circumstantial evidence, and may order amendments to a contract.

It also said the new provisions will be applicable to tenancy contracts and movable properties affected by the pandemic.

It clarified that if, due to the pandemic, a tenant was unable to use the leased property, in whole or in part, the court would reduce the rent as much as the usually intended benefit was reduced.

A lessor, meanwhile, does not have the right to terminate the contract if a tenant is late in paying rent for the period during which it was impossible to fully or partly use the property due to the pandemic.

HIGHLIGHT

The Supreme Court said a competent court will issue its verdict based on facts and circumstantial evidence, and may order amendments to a contract.

The new regulations also cover construction contracts, supply contracts, and the like, which have been affected by the pandemic.

If the pandemic causes an increase to the cost of materials and labor wages, etc., the court shall increase the value of the contract while ensuring the obligor can afford to bear the expense. The obligee, upon increasing the obligation, has the right to request the termination of the contract. If the increase in the cost of materials is temporary, the court reserves the right to temporarily suspend the contract.

If the pandemic causes a shortage of material in the market, the court can reduce the quantity to the extent it deems sufficient to protect the obligor from harm.

Moreover, if the shortage of materials is temporary, the court can temporarily suspend the contract if the person obligated to it is not severely affected by this suspension. If he is harmed, he may request termination of the contract. If the materials were not available at all, leading to the impossibility of implementing the contractual obligations or some of them, the court will terminate the clauses that are impossible to implement upon the request of one of the parties to the contract.

If a contract obliges one of the parties to carry out a task, which cannot be completed on time due to the pandemic, the court can temporarily suspend the implementation of the obligation. If the other party fears unusual damage due to the suspension, he may request termination of the contract.

In addition, the court also stressed the need to carefully assess the damages on a case-to-case basis, and that one or more experts should do the assessment. While assessing damages, it should be made clear what losses were incurred directly due to the pandemic and had nothing do to with seasonal upswing in certain activities.

The Supreme Court explained that a court is bound, when considering cases arising from contracts and obligations affected by the pandemic, not to apply penalty clause or fines in whole or in part — depending on the case.

In the event that a contract includes a clause of exemption from liability for one of the contracting parties when an emergency or force majeure occurs, the condition has no effect, and the party that breaches the obligation must provide evidence that the pandemic was the reason for the breach.

The affected contracts that are not covered by the provisions of this principle shall be subject to the legal and statutory litigation principles, said the court.

Commenting on the decision, Talal Albotty, the regional director of the Central Region, Salama Insurance Co., said there is a type of insurance called “suspension of operations” because of continuous epidemics, and falls under property insurance.

“This type of insurance can be found in European countries and some Asian countries but it is not applicable in Saudi Arabia,” he told Arab News. “The insurance against projects does not exist because when the project stops, insurance stops.”

Regarding the rise in prices of commodities, or the increase in prices because of pandemics and suspension of imports, a condition must be added stating that the value of property or project must increase by 10-25 percent, he added.

“Now most reinsurance companies around the world stopped offering insurance related to pandemics and contagious diseases in most countries, including COVID-19, because their impact was huge and the companies sustained huge losses,” he said.

Saudi lawyer Reem Alajmi said the resolution aims to treat and remedy the losses incurred by parties to the contract in terms of obligations.

“The parties could not fulfil their obligations because of a lack of sufficient resources or suspension of working hours during the pandemic. Fulfilling the obligation fully or partially was difficult because COVID-19 pandemic was a force majeure,” she told Arab News.

According to Alajmi, the effects or damage caused by the pandemic must not be covered by other laws. “Proving the occurrence of damage is the responsibility of the plaintiff and the defendant based on evidence submitted to the court,” she added. “The contracts and obligations are amended accordingly.”