RIYADH: A contractor who duped the government while undertaking a SR160 million bridge project has been ordered by the National Anti-Corruption Commission (Nazaha) to redo the project.
Nazaha found out that the Transport Ministry contractor made trestles for rainwater dispersal instead of a bridge on the Abha-Nammas dual road in the Asir region.
A probe, covering the contractor and other officials, is underway to fix responsibility in the case in preparation for its referral to investigation authorities.
Nazaha received a report on the irregularities concerning non-application of contractual specifications and standards, said Nazaha spokesman Abdulrahman bin Ahmed Al-Ajlan.
The anti-graft body asked the ministry to look into the matter and spell out penalties for those responsible, said Al-Ajlan.
Nazaha received the results of the investigation that showed what the contractor had done was not approved by the ministry.
Nazaha found out that the Transport Ministry contractor made trestles for rainwater dispersal instead of a bridge on the Abha-Nammas dual road in the Asir region.
A probe, covering the contractor and other officials, is underway to fix responsibility in the case in preparation for its referral to investigation authorities.
Nazaha received a report on the irregularities concerning non-application of contractual specifications and standards, said Nazaha spokesman Abdulrahman bin Ahmed Al-Ajlan.
The anti-graft body asked the ministry to look into the matter and spell out penalties for those responsible, said Al-Ajlan.
Nazaha received the results of the investigation that showed what the contractor had done was not approved by the ministry.